Three-Point Estimation #
Three-Point Estimation is a technique used in project management and Agile methodologies to estimate the duration or effort required to complete a task or user story. It involves estimating three values:
1. Optimistic Estimate (O): The best-case scenario where everything goes better than expected.
2. Pessimistic Estimate (P): The worst-case scenario where everything goes wrong.
3. Most Likely Estimate (M): The most probable scenario based on normal conditions.
The final estimate is calculated using these three values to provide a more realistic and comprehensive view of the task’s effort or duration.
Formula #
The final estimate (E) is calculated using the formula:
E=O+4M+P6E = \frac{O + 4M + P}{6}E=6O+4M+P
This formula is known as the Program Evaluation and Review Technique (PERT) estimate, which provides a weighted average, giving more weight to the most likely estimate.
Steps of Three-Point Estimation: #
1. Identify the Task:
– Select the task or user story to be estimated.
2. Estimate the Three Values:
– Optimistic Estimate (O): Estimate the minimum effort/duration if everything goes perfectly.
– Pessimistic Estimate (P): Estimate the maximum effort/duration if everything goes wrong.
– Most Likely Estimate (M): Estimate the effort/duration under normal conditions.
3. Calculate the Final Estimate:
– Use the formula to calculate the final estimate.
4. Record the Estimate:
– Document the final estimate and the individual estimates (O, P, M).
Example of Three-Point Estimation for an E-Commerce Website #
Scenario: The team is estimating the effort required to implement a “Checkout Process” feature for an e-commerce website.
Participants:
– Product Owner: Eva
– Development Team: Alice (Frontend Developer), Bob (Backend Developer), Carol (QA Engineer)
– Scrum Master: Dave
User Story:
ID: PBI-005
Description: As a user, I want to complete my purchase through a secure and user-friendly checkout process.
Acceptance Criteria:
– Users can review their cart items before checkout.
– Users can enter shipping information.
– Users can choose a payment method and complete the payment securely.
– Users receive a confirmation email after successful checkout.
Three-Point Estimation Session: #
1. Identify the Task:
– The team selects the “Checkout Process” feature for estimation.
2. Estimate the Three Values:
Optimistic Estimate (O):
– Alice: “If everything goes smoothly, we can finish the frontend in 3 days.”
– Bob: “The backend integration with the payment gateway might take 2 days.”
– Carol: “QA testing could be completed in 1 day if there are no major issues.”
– O = 3 + 2 + 1 = 6 days
Pessimistic Estimate (P):
– Alice: “If we encounter UI issues, the frontend might take up to 6 days.”
– Bob: “Payment gateway integration issues could take 5 days.”
– Carol: “QA testing might take 4 days if we find significant bugs.”
– P = 6 + 5 + 4 = 15 days
Most Likely Estimate (M):
– Alice: “Under normal conditions, the frontend should take 4 days.”
– Bob: “Backend integration is likely to take 3 days.”
– Carol: “QA testing should take 2 days.”
– M = 4 + 3 + 2 = 9 days
3. Calculate the Final Estimate:
– Using the PERT formula:
– E=O+4M+P6E = \frac{O + 4M + P}{6}E=6O+4M+P
– E=6+4(9)+156E = \frac{6 + 4(9) + 15}{6}E=66+4(9)+15
– E=6+36+156E = \frac{6 + 36 + 15}{6}E=66+36+15
– E=576E = \frac{57}{6}E=657
– E=9.5 daysE = 9.5 \, \text{days}E=9.5days
4. Record the Estimate:
– The final estimate for the “Checkout Process” feature is 9.5 days.
Summary of Three-Point Estimation: #
User Story ID | Description | Optimistic (O) | Most Likely (M) | Pessimistic (P) | Final Estimate (E) |
PBI-005 | Checkout Process | 6 days | 9 days | 15 days | 9.5 days |
Benefits of Three-Point Estimation: #
– Comprehensive View: Accounts for variability and uncertainty in task estimation.
– Improved Accuracy: Provides a more realistic estimate by considering best, worst, and most likely scenarios.
– Risk Management: Helps in identifying potential risks and their impact on the project timeline.
– Team Collaboration: Encourages team members to discuss and consider different aspects of the task.
Conclusion #
Three-Point Estimation is a valuable technique in Agile for estimating the effort or duration required to complete tasks. By considering optimistic, pessimistic, and most likely scenarios, this method provides a more accurate and realistic estimate, helping teams manage uncertainty and plan effectively. The example of estimating the “Checkout Process” feature for an e-commerce website demonstrates how Three-Point Estimation facilitates informed decision-making and consensus-building within the team.